- DL5190.4-2012电力建设施工技术规范第4部分:热工仪表及控制装置(英文版)
- 中国电力企业联合会
- 558字
- 2021-03-29 04:33:15
Foreword
This Part is revised from DL/T 5190.5-2004"Specification for thermal power erection and construction-Part 5:Section of instrumentation and control"by Professional Technical Committee on Thermal Power Construction of Standardization Administration of China,in association of relevant organizations according to the requirements of Document GUONENGKEJI〔2009〕No.163"Notice of National Energy Administration on Formulating(Revising)the First Batch of Professional Standard in the Energy Field in 2009".
DL 5190"Technical specification for thermal power erection and construction"comprises the following 9 parts:
DL 5190.1 Part 1:Civil Work
DL 5190.2 Part 2:Boiler Unit
DL 5190.3 Part 3:Steam Turbine Generator Units
DL 5190.4 Part 4:Instrumentation and Control
DL 5190.5 Part 5:Pipe and System
DL 5190.6 Part 6:Water Treatment and Hydrogen Generation Equipment and System
DL 5190.7 Part 7:Welding
DL 5190.8 Part 8:Processing Preparation
DL 5190.9 Part 9:Hydro-structure
This Part is the fourth part"Instrumentation and Control"of DL 5190(hereinafter referred to as"this Part").
The main contents of this Part include:General Principles,Basic Regulation,Installation of Sampling﹠ sensitive element,Installation of Local Measuring ﹠ Control Instrument,Installation of Control Panel(Console,Box,Cabinet),Laying and Wiring of Wires and Cables,Pipe Laying Work,Protection and Grounding,I﹠C Device Commissioning and appendixes.
This Part has the followingmain technical changes compared with DL 5190.5-2004:
—The compulsory provisions were specified;
—The contents on"pneumatic local-mounted instrument"in the former specification were deleted;
—Section 5.3"Computer and Auxiliary System Installation"was added in Chapter 5;
—The contents on the requirements for the technical data,like"list of installation records of thermal control equipments"and"list of commissioning records of thermal control equipments",were added in Chapter 9;
In this Part,Article 3.1.6 and Item 1~Item 3 in Article 8.4.12 printed in bold type are the compulsory provisions and must be enforced strictly.
This Part was proposed by the China Electricity Council.
This Part is under the jurisdiction of the Professional Technical Committee on Thermal Power Construction of Standardization Administration of China.
Chief Development Organizations:
The First Northeast Electric Power Engineering Co.and SEPCOIII Electric Power
Construction Corporation.
Participating Development Organizations:
Hebei No.1 Electric Power Construction Company,Guangdong Power Engineering
Corporation
The First Electric Power Construction Company of Jiangsu Province and Huaneng Power
International Inc..
Chief Drafting Staff:
Fan Youlin Han Yingming Liu Qiang Li Yajuan Ju Zhiqiang
Sun Lijie Gao Jihong Pei Sheng Chen Hongjun Wu Hechun
Lai Zhengmin.
Chief Examiners:
Jia Yanbing Duan Ximin Chen Fayu Luo Jiacong Ma Jun Dai Guang
Liao Guanghong Wang Wenxiang Chen Jikun Sun Huafang Gao Zhicun
Jiang Shouyi Zhang Gang Qian Youyi Xu Tongshe Chen Kuanhong
Wang Junshan Wan Hui Ji Wenjun Luo Zhihao Bao Jiagui Liu Wenxin
Chen Zude
This Part shall replace DL/T 5190.5-2004"Specification for thermal power erection and construction-Part 5:Section of instrumentation and control"from the implementation date hereof.
During the process of implementing this Part,the relevant opinions and advices,whenever necessary,can be fed back to the China Electricity Council Standardization Center(Address:No.1,Baiguang Road Ertiao,Beijing,100761,China).