Foreword

This Part is revised from DL 5011-1992"The Code of Erection and Acceptance of Electric Power Construction Section of Steam Turbine Set"by Professional Technical Committee on Thermal Power Construction of Standardization Administration of China,in association of relevant organizations according to the requirements of Document GUONENGKEJI〔2009〕No.163"Notice of National Energy Administration on Formulating(Revising)the First Batch of Professional Standard in the Energy Field in 2009".

DL 5190"Technical specification for thermal power erection and construction"comprises the following 9 parts:

DL 5190.1 Part 1:Civil Work

DL 5190.2 Part 2:Boiler Unit

DL 5190.3 Part 3:Turbine Generator Unit

DL 5190.4 Part 4:Instrumentation and Control

DL 5190.5 Part 5:Piping and System

DL 5190.6 Part 6:Water Treatment and Hydrogen Generation Equipment and System

DL 5190.7 Part 7:Welding

DL 5190.8 Part 8:Processing Preparation

DL 5190.9 Part 9:Hydro-structure

This part is Part 3"Turbine Generator Unit"of DL 5190.

The main contents of this Part include:general provisions,terminologies,basic provisions,steam turbine,generator and excitation device,regulation and protection device and oil system,pipes in the scope of steam turbine,auxiliary equipment,accessory machinery,bridge crane,insulation for steam turbine,enclosure,adjustment of turbo-generator,startup,trial run,appendices,notes on standard words and phrases,quotation of standards and notes on clauses.

This Part has the following main technical changes compared with DL 5011-1992:

—The compulsory provisions were specified;

—The scope of application has bee adjusted to"turbo-generator units in fossil fuel power plants,gas and steam combined cycle turbo-generator units,turbo-generator units in nuclear power plants",without defining the unit capacity and parameters.

The following has been added:

—Relevant provisions on embedded pad blocks and installing concrete cushion blocks for turbine;

—Relevant provisions on installation of elastic vibration insulating foundation;

—Provisions on welding and combination of large LP outer cylinder without soleplate support,installation of 1000MW class units supplied with integrated HP casing and IP casing and hydraulic turning gear;

—Installation process requirements for"four-pad tilting pad"and"six-pad tilting pad"radial bearings;

—Installation process requirements for"Kingsbury thrust bearing"and"half-ring thrust pad";

—Installation process requirements for adjustable seals of turbo-generator;

—Grouting process and curing requirements for high strength non-shrinking grouting materials;

—Provisions on installation of EH regulating and HP fire-resistant oil pipes;

—Installation process requirements for stainless steel cooling tubes of condenser and installation process requirements for air cooling devices;

—Installation process requirements for air-cooling fans;

—Provisions on air cooling unit vacuum system leakage test and flushing of air-cooling system;

The following has been deleted:

—Relevant provisions on asbestos gaskets and Freon gas and other materials explicitly prohibited to use by the state in the original specification;

—Turbine instruments in the original specification.

In this Part,Items 2 and 3 of Article 3.3.5,Article 4.1.5,Article 4.1.6,Article 4.9.3,Article 5.1.11,Item 4 of Article 5.3.7,Item 1 of Article 5.5.8,Item 10 of Article 5.6.9,Item 1 of Article 5.8.5,Article 6.1.5,Article 6.1.6,Article 6.2.15,Article 6.7.5,Article 7.3.2,Article 7.3.6,Items 1 and 10 of Article 8.2.9,Item 9 of Article 11.3.1,Item 9 of Article 11.9.3,Item 1 of Article 11.10.6,Items 1 and 2 of Article 11.10.8 in bold face are compulsory provisions,and must be implemented strictly.

This Part was proposed by the China Electricity Council.

This standard is under the jurisdiction of the Standardization Technical Committee on Thermal Power Construction of the Power Industry.

Chief preparation organization:

Jiangsu Electric Power Construction No.3 Engineering Company

Participating development organizations:

Tianjin Electric Power Construction Company,

Hebei Electric Power Construction No.1 Engineering Company,

Anhui Electric Power Construction No.2 Engineering Company,

Henan No.1 Thermal Power Construction Company and Beijing Electric Power

Construction Company.

Chief drafting staff:

Zhao Zhuren Xu Yunquan Yu Xiaoming Hao Qingfeng Zhang Qingnian

Liang Hao Xie yonghui Zhang Xuefeng Wang Zhiyong.

Main review staff:

Fan Youlin Cui Yukui Yan Zizheng Wei Min Zhou Liang Lu Huanhao

Yang Shunhu Yu Haimiao Wang Zuo Qian Ping Lv Yanfu Lu Xinhuai

Wang Jiayong Han Chengwei Wang Yanyun Shi Ying Liu Chunxiao

Shen Chun Hua Zemin Ling Hejin Ma Xiaozhen Wang Hanhong

Chen Zhanhong Ding Lianhe Li Ning.

After implementation,this part shall substitute"The Code of Erection and Acceptance of Electric Power Construction Section of Steam Turbine Set"DL 5011-1992.

Please feed back any comment or suggestion arising from the implementation of this part to the Standardizing Center of China Electricity Council(2-1 Baiguang Road,Beijing,Zip:100761).

English translators:Meng Lixue,Jiang Hong,Chen Yanfang

Chief reviewers:Zhu Qiansheng,Zeng Qingmeng,Wang Hongliang