9.2 Rail Chair
General Items
9.2.1 The allowable deviation for installation of rail chair shall comply with the requirements in Table 9.2.1(see Figure 9.2.1).
Quantity to be checked:100%.
Inspection method:See Table 9.2.1.
Table 9.2.1 Allowable deviation for installation of rail chair
Figure 9.2.1 Schematic drawing for installation of rail chair
1,2-rail chair;3-horizontal base line of rail chair(center line);4-horizontal center line of electric arc furnace;
5-base mark of elevation;6-longitudinal base line(center line)of rail chair(at electrode side)