7.3 Removable Hood

Ⅰ Dominant Items

7.3.1 After completed installed,the removable hood shall be involved in the hydrostatic test of the system,which shall comply with the requirement of the design technical document.

Quantity to be checked:100%.

Inspection method:Observe,and check the record of pressure test.

Ⅱ General Items

7.3.2 The allowable deviation for installation of removable hood shall comply with the requirements in Table 7.3.2.

Quantity to be checked:100%.

Inspection method:See Table 7.3.2.

Table 7.3.2 Allowable deviation for installation of removable hood

img